SAFEGUARD | Rebranding in a Tight Urban Environment
A two-phase rebrand that required careful planning around limited site access, local sign code and city inspections.
The Project
When Safeguard Self Storage acquired a facility in Brooklyn, New York, the property needed to be transitioned to the Safeguard brand. In a dense urban setting where space around the building was limited, even routine installation logistics required additional planning.
The project was divided into two phases. Temporary signage and removal of the existing signs would support the initial brand transition, followed by permanent signage once permitting, fabrication and site coordination were complete.
Local sign code also shaped the final sign package. The primary sign on the front of the building could be illuminated, while signs on the side elevations could not. The signage was adapted accordingly, maintaining a consistent Safeguard identity while meeting the requirements for each elevation.
Planning Around a Tight Brooklyn Site
The first phase began in December with removal of the existing signage and installation of temporary banners. The work was scheduled for Christmas Eve, adding another consideration to an already challenging urban installation.
Garages, parked vehicles and limited sidewalk space surrounded the facility, leaving little room for the equipment needed to reach the building. Each side elevation required an 80-foot articulating lift, making access and positioning especially important.
Those conditions also meant the installation plan had to remain flexible. On the morning of the first installation, a vehicle was parked where the lift needed to be positioned. The crew coordinated with the team on site, but the area could not be cleared in time to complete that portion of the work. Rather than compromise the installation, the crew returned once the necessary access was available.
That first phase provided a clear understanding of the site’s constraints before the permanent signs arrived.
From Permanent Installation to Final Closeout
By March, the permanent signage was ready for installation. With the site’s access requirements already established, the new sign package was installed with the illuminated identification on the front of the building and non-illuminated signage along the side elevations.
The physical installation was complete, but the project still had one important step remaining.
Egan reviewed the project and found that the required electrical inspection had not yet been completed. What followed was several months of coordination with the city to get the remaining inspection scheduled and completed.
When the inspector arrived, the team encountered another site-specific consideration. The illuminated sign was connected to Safeguard’s third-party control system, so operating the sign for the inspection required coordination beyond simply accessing a local switch.
The electrical inspection was ultimately completed in September, bringing the permitting process to its final stages.
Managing the Details Through the Finish Line
The Safeguard Brooklyn rebrand demonstrates how the challenges of a signage project can extend beyond fabrication and installation. In this case, limited access influenced how crews approached the building, local code determined how signage could be illuminated, and city inspections continued months after the signs were installed.
Managing those moving pieces required staying involved from the temporary brand transition through permanent installation and permitting closeout. The result was a Safeguard-branded facility designed around both the building itself and the realities of operating in a dense Brooklyn neighborhood.