SMARTSTOP | Southwest Freeway Project

High-Rise Signage, Ground-Level Coordination

Taking Full Advantage of a High-Profile Location
When SmartStop acquired a 176-foot-tall self-storage facility along Houston’s Southwest Freeway, the rebrand presented an opportunity to make the most of a highly visible location.

With the building positioned along Houston’s busy Southwest Freeway, the signage plan had to balance scale, placement and installation feasibility. Three large signs were strategically positioned to identify the facility from multiple directions, including two 10′ x 20′ signs near the top of the 176-foot building and a 160″ x 320″ sign at the entrance.

Four Hours to Get It Done
Installing signage near the top of a 176-foot building required significantly more coordination than a typical rebrand.

Each elevated sign was installed using a swing stage, with the east and west elevations completed on separate days so the equipment could be repositioned. Work also required road and lane closures, traffic control and police coordination with the City of Houston.

The city limited each road closure to a four-hour window, leaving little room for delays once work began. High winds added another variable, affecting staging during an already restricted installation schedule. The team had to work within both the city’s time limits and changing site conditions to safely complete each elevation.

A Challenge Hidden Behind the Storage Units
The exterior wasn’t the only part of the property that required careful planning.

During the initial survey, Egan identified several storage units that would need to be accessed during installation to reach the existing electrical serving the signs. As the project progressed, those units became occupied, adding another layer of coordination before installation could move forward.

With customer belongings now limiting access to the existing power supplies, Egan and SmartStop coordinated with the affected customers so crews could complete the installation. But solving the immediate access issue wasn’t enough. Leaving the power supplies in their existing locations would create the same challenge every time the signs required electrical service.

Egan recommended relocating the power supplies to accessible common areas wherever possible. Future electrical service can now be completed without entering occupied storage units or disrupting customers.

For a facility designed around secure individual storage spaces, that change turned a difficult existing condition into a more serviceable solution for the property moving forward.